Rendering Image of proposed design for BRT Station Hushnagri

The project was initiated on 8 February 2016 and was to be completed by 27 January 2017. However, after the initial meeting with the Chief Minister of KPK Province, it was decided to complete preliminary design work by the end of June 2016, thus enabling Detailed Engineering Design work to start, and construction to start as early as January 2017 for completion in December 2017.

 